Demolition of the equipment of tobacco manufacture in Moscow

From January, 3 till February, 17, 2012, the experts of “100 tonn – service” performed a complex of works on demolition of the equipment of tobacco manufacture at factory Java in Moscow under the order of British American Tobacco, JSC.
Within the project scope the following operations were done: partial demolition of communications, manufacturing of fixture, demolition of the equipment, mounting on pallets, fastening to pallets, packing into a film, moving to a remote platform, lowering into a court yard, moving to a loading place, loading on a motor transport and fastening of pallets among themselves. Several pieces of the equipment were moved to another floor and mounted there once again, another part of the equipment was utilized by cutting. Totally there were performed works at 12 technological lines, about 15 equipment units in each line, unit weight– from 3 up to 8 tons. Complexity of the project consisted in constrained conditions of the operating manufacture in the centre of Moscow.