Four gas-generator plants WÀRTSILÀ installed

    In June 2016 our Company (100 TONN MONTAZH) unloaded, de-preserved, performed SKD assembly and installed four gas-generator plants Wartsila onto vibration mounts in Kazakhstan. Due to the use of a GP500 gantry system, the primary contractor managed to start installation of the equipment directly on completion of installation of load-bearing metalware of the building with simultaneous installation of the sandwich-panels. This technology considerably decreased the timelines of the works implementation. Our designers implemented an interesting technical solution, that enabled them to further accelerate the works. Prior to use the trawl for unloading, a section of the gantry tracks had been dismantled, and after the load was lifted and the trawl left the premises, this section was installed back to its place and the gantry system started to move along it with the load. The works were rather difficult for execution due to simultaneous implementation of construction and installation works at the site, as well as due to necessity to keep up with precise positioning of the gas-generator plants onto vibration mounts (1 mm tolerance). Thorough engineering of the operations, experience in handling Wartsile equipment and well-coordinated teamwork enabled our Company to perform all the operations in accordance with an approved work schedule.