Machinery lifted at Voronezh Cable Plant

    In January 2017, our Company (100 TONN MONTAZH) lifted and secured a cage (14 tonnes, 6 meters long) in confined space of an operating cable plant. The aim of the works was service repairs of the Customer’s machinery by the representatives of the French supplier. On completion of the works, the cage was installed back to its place within four hours after the Customer’s call. We used the smallest 60-tonne-capacity gantry system for these works. In 2015 our Company performed similar works for POURTIER S.A.S., Ltd.