Parts of machining centre TBT unloaded and mounted in Yekaterinburg

    In the period from December 2013 to February 2014 our Company (100 TONNE SERVICE) unloaded and mounted four parts of a machine bed (TBT, Germany) at the production site of Construction Company SMU-30 (OOO). Within the framework of the project our specialists developed and implemented a complex project solution pertaining to installation of our 125-tonne hydraulic gantry system, as well as manufactured special equipment for slinging the equipment to be mounted.