Melting furnace and three casting machines set to final position in Karelia

Our specialists (100 TONN MONTAZH) unloaded a 26-ton melting furnace (Marconi, Italy) and three casting machines (32 tons each, Buhler Druckguss AG) from the loaders and set them to final position in Nadvoitsy, Republic of Karelia.
The works were rather difficult for execution due to the arrival of the equipment in breach of the sequence stipulated in the Agreement, as well as due to the presence of a large number of technological channels (pits). Nevertheless, all the works were accomplished on a professional level in due time. See section Projects for more details.