Unloading and installation of boilers BOSCH (Shymkent, Kazakhstan)

In the period from December 22 to December 25, 2014 the specialists of our Company (100 TONNE MONTAGE) unloaded five 86-tonne boilers BOSCH from the transport vehicles, turned them to 90° and set to final position on a foundation in Shymkent, Kazakhstan, on request from Instar Logistics (TOO, Republic of Kazakhstan). The space for operations was limited by the pits within the operation site. Total mass of installed equipment is 350 tonnes. The use of extra high strength 18-meter beam and 24-meter gantry system track together with extensive practical experience and high level of professionalisms of our specialists enabled our Company to fulfill the works within 4 days.