HANKOOK VTC-30/40E machine unloaded, shifted to the installation site and assembled

In the period from 9 JAN 2017 to 30 JAN 2017, our Company (100 TONN MONTAZH) unloaded the HANKOOK VTC-30/40E machine (South Korea) from vehicles, shifted it to the installation site and performed its SKD assembly. A 125-tonne-capacity hydraulic gantry system GP 125 was used for SKD assembly. The heaviest part of the machine, i.e. its body, is 24 tonnes. Tipping of the columns into vertical position in confined space of the workshop was the most complicated operation.
The works were accomplished in due time.