13 Jul 2016

ДА2243 hydraulic press assembled in Kamensk Uralsky

Within the period from May 25 to June 4, 2016 on request from Machine-Building Enterprise PressMash, our Company (100 TONN MONTAZH) continued the works pertaning to ДА2243 hydraulic press assembly, i.e. unloading, shifting and element-by-element assembly of a 100-ton ДА2243 hydraulic press (manufactured by PressMash, Russia). A 125-ton-capacity GP125 gantry system and a 40-ton workshop trailer were used for the works within the KULZ premises (Kamensk Uralsky Foundry, OAO) in Kamensk Uralsky, Sverdlovskaya Oblast.

29 Jun 2016

Pod drives installed aboard Vsevolod Bobrov vessel

In July 2016 our Company (100 TONN MONTAZH) unloaded, shifted, lifted and set to final position two pod drives (manufactured by Steer Prop; 163 tons each) at the production site of Severnaya Verf dockyard in St.Petersburg.

To set the pod drives to final position, roll and trim must be created in confined space under the stern of the vessel. The works are complicated due to the presence of small and large propellers both installed on each pod drive. The works were accomplished in accordance with the approved schedule. It must be noted that this was the second project of pod drives installation, and the Customer again expressed his gratitude for our professionalism.

24 Dec 2015

Manufacturing lines relocated in Syzran

In August 2015 our Company (100 TONNE MONTAGE) dismantled, relocated and mounted pouring and thermoforming lines at Avtokomponent Plant in Syzran. The works had to be accomplished within short timelines during AvtoVAZ company holidays (Customer of Avtokomponent Plant).

The following operations were carried out within the framework of the project: cases of the pouring modules were took to pieces, gantry robots and presses were dismantled; then they were loaded onto transport trolleys, shifted into a new workshop, assembled and mounted. Thermoforming lines were
also dismantled, loaded onto transport trolleys, shifted into a new workshop and mounted. All the works were accomplished in due time.

20 Nov 2015

Machining centres GROB unloaded, shifted and mounted in Samara

In November 2015 our Company (100 TONNE MONTAGE) unloaded, shifted and set to final position two machining centres GROB (Germany) at BOSCH Plant in Samara. The Customer asked to speed up the process to avoid downtime of expensive transport vehicles. Each 24-tonn machining centre required delicate handling. The works were accomplished in due time.

15 Sep 2015

Manipulator dismantled, shifted and mounted in Tikhvin

Within the period from August 10 to August 14, 2015 our specialists dismantled manipulator Clansman, shifted it and mounted it within the premises of Tikhvin Freight Car Building Works Plant (TVSZ) in Tikhvin, Leningradskaya Oblast. The works were performed in a very confined space with application of two supports of GP125 gantry system. Our specialists managed to complete the works ahead of schedule, which allowed the personnel of the plant perform setting-to-work operations and minor repairs of the manipulator before the start of production.