CHI NING press mounted in Tatarstan

    On 08 JUL 2015 our Company on request from Solver carried out operations within the framework of the first stage of mounting procedures with a 800-tonne press (CHI NING, Taiwan) at OAO POZiS in Zelenodolsk (Tatarstan). A 125-tonne-capacity hydraulic gantry system and a 450-tonne-capacity turntable were used to unload heavy parts of the press (80 and 45 tonnes each) from the vehicle, turn them to 90 degrees, shift to the installation site and set to final position according to the project one onto another. The second stage of operations included assembly of the engine, flywheel and shaft (total mass of 32 tonnes). The operations were carried out in the presence of installation Taiwanese supervisors and were performed in strict compliance with our Project for implementation of construction operations. The works were fulfilled in a room with relatively low roofing in two stages (three and two days long, respectively).