Equipment unloading and placement at factory Nevyanskiy Tsementnik

    By company “Logis” order the works have been executed in city of Nevyansk, Sverdlovsk region. The scope of works: unloading and placement for storing of power-generating rquipmet produced by Wärtsilä and ABB. Three generators weghting 30tons each and three gaz-reciprocating engines weighting 83 tons each were unloaded from a heavy-load truck and moved into storehouse. Gantry system GP125H has been used for the works carrying out. Handling operations lasted for 5 days.