Two plants producing components for LG and SAMSUNG plants relocated to new sites

In the period from May, 10 to July 23, 2016, our Company (100 TONN MONTAZH) on request from D.A. Rus (OOO) dismantled, relocated and installed machinery for production of components for LG and SAMSUNG plants to new sites. The works were fulfilled in two stages.

The first stage (May, 10 to May 17, 2016) included dismantling of 11 automatic molding machines, their package and loading into containers for further dispatch to Vietnam. The works were performed within the premises of LG plant in Dorokhovo, Moskovskaya Oblast. The works were carried out in the shortest possible time.

Within the second stage from June 10 to July 23, 2016 our specialists on request from D.A. Rus (OOO) dismantled, packed, relocated and installed the machinery at a new site. 12 automatic molding machines were relocated to a new site (Vorsino, Kaluzhskaya Oblast) from the LG plant premises. Industrial rubber components production workshop (25 pieces of machinery) and automatic molding machines workshop (9 pieces of machinery) were relocated to a new site. Besides, auxiliary machinery from both workshops was also dismantled, relocated and installed at a new place.

Our specialists installed all pieces of the machinery at a new site and performed its cold start.