Heat exchanger and steam generator set to final position within the premises of Antipinsky Oil Refinery

In the period from 8 AUG to 17 AUG 2016, on request of Construction Company Tekhinzhstroy, our Company (100 TONN MONTAZH) set to final position a 33-tonne heat exchanger and a 20-tonne steam generator within the premises of Antipinsky Oil Refinery. Each piece of the machinery was lifted and set to the project position +7200. The unique feature of the works is a simultaneous operation of a 120-tonne-capacity autocrane and G60 gantry system. All the works were performed in confined space of the residue destruction shop with no standard load-lifting mechanisms available.