General Electric gas turbine power units installed at Talakhovskaya and Mayakovskaya Central Heating and Power Plants in Kaliningradskaya Oblast

In the period from 6 OCT 2016 to 05 FEB 2017, our Company (100 TONN MONTAZH) set on a foundation four sets of General Electric gas turbine power units at Talakhovskaya and Mayakovskaya Central Heating and Power Plants (CHPP) in Kaliningradskaya Oblast. Each gas turbine power unit consists of three parts, i.e. turbine, generator and reducer. Total mass of the assembled equipment is 975 tonnes. GP500 hydraulic gantry system was used for operations. In the harshest conditions of the construction site of the electric power stations our specialists (100 TONN MONTAZH) showed their high qualification and skills that allowed them to carry out all the works in strict compliance with the work schedule moving from one station to another and using only one gantry system.