Turbine and electric generator GENERAL ELECTRIC at Novomoskovsk GRES

At the end of February – beginning of March engineers of company 100tonn-service have accomplished the following works: moving from stock to the place of mounting and assembling on the basement of electric generator General Electric at Novomoskovsk GRES.

The turbine weight – 202tons, the generator weight – 177tons. The works were performed in accordance with the works execution project which was carried out by 100tonn-service. The plan was approved both by the customer (Tsentroeneromontazh, JSC, Minsk) and prime contractor (Energokaskad, CJSC, Moscow).

The following equipment has been used for the works execution: gantry lifting system MP320 with lifting capacity of 320tons, modular platforms Scheuerle and other special equipment. The works lasted 2.5weeks.