Mounting of Siemens turbine and gas turbine generator, Mosenergo

In August 2013 our engineers unloaded from automobile truck and installed turbine SGT5 PAC 4000F and gas turbine generator SGen5-1000A , manufactured by Siemens. The works lasted 12 days since August, 5th, till August, 16th, at work site of Mosenergo, OJSC – power block CCP TPP-20 (Moscow).
The total weight of installed equipment was 610tons.