Unloading, moving and mounting of medical equipment in Tver

    From January, 18 till February, 29, 2012, the experts of “100 tonn – service” performed unloading from motor transport, moving to a mounting place and mounting of the medical equipment Bosch (Germany) for expansion of manufacture of infusion solutions at the factory of the company in Tver under the order of Gematek Ltd.

    The work was carried out in some stages in process of delivery of motor transport with the equipment. In total about 40 units of the equipment with total weight 85 t were unloaded, moved and mounted. Some units of the equipment were turned from horizontal to vertical position during mounting. The heaviest unit (a sterilizer) weighed 12 t and was mounted on a project site into an areaway with depth of 900 mm.